Nepal’s Energy Ministry has scrapped licenses of three power developers financed by Indian companies, reports Online Khabar.
The Details:
- The projects that have been affected are 130 MW Budhi Gandaki ‘A’ and 260 MW Budhi Gandaki ‘B’ and 350 MW Dudhkoshi.
- The Budhi Gandaki projects were to be developed by Naulo Nepal Hydro Electric Pvt Ltd, a company backed by Indian financing while the Dudhkoshi project was given to KBR India Infra Pvt Ltd.
- The ministry has given them letters on August 21 to present their financial closure reports and draft Power Purchase Agreements (PPA) at the earliest.
- But the companies could not present important documents such as the proof of registration of a company, projects’ financial closure report and a draft of the power purchase agreement.
- Naulo Nepal received its license in 2008 and KVR Infra in 2010.
Editors Recommendations
- Upper Tamakoshi Hydropower Project to Miss its Deadline of This July
- PM Oli wants to Revive Budhigandaki Hydropower Project
- Local Government to Issue Licenses for Hydropower Projects
The Latest
-
Xiaomi 14 Review: Best Phone Under Rs. 1 Lakh in Nepal!Xiaomi 14 Review: TechLekh Verdict The Xiaomi 14 stands out as one of the best…
-
WorldLink Reaches 9 Lakh Households; 900,000th Customer Receives Incredible GiftsHIGHLIGHTS Worldlink’s 900,000th customer received surprise gifts from Shrinkhala Khatiwada. Worldlink is currently operating in…
-
Tecno Spark 20C with Dual Speaker Launched in NepalHIGHLIGHTS The Tecno Spark 20C price in Nepal is Rs. 15,990 (8/128GB). The smartphone has…