In the past couple of years, there has been a significant rise in the cost of construction materials. Due to which, the cost of building the Motihari-Amlekhgunj oil pipeline has gone up by at least 15% as compared to the estimated price on the former agreement of the project, reports The Himalayan Times.
The Backstory:
- An official agreement was signed in August 2015, between the government of Nepal and India for the oil pipeline which put the overall cost of the 36-kilometer-long project at Rs. 4.40 billion.
- As per the agreement, India would contribute Rs. 3.2 billion to the project, and the rest of the cost would be covered by Nepal.
- The deadline for the completion of the project was 30 months.
- However, the project has only just gained momentum in the past couple of months, after having remained dormant for nearly two and a half years.
- The Indian Oil Corporation (IOC) and other agencies appointed by IOC for the project have started unloading the pipes along the finalized route.
Why it matters:
- The price hike puts more pressure on the Nepal government.
- As per the agreement, India has already decided to contribute Rs. 3.2 billion for the project, and the rest of the fund will have to be provided by Nepal.
What they are saying:
- Owing to inflation of construction materials required for the project like pipes, rods, cement and labor costs, among others, in the past couple of years, the cost of the cross-border petroleum pipeline has climbed much higher today, informed a highly placed source at Nepal Oil Corporation (NOC) to The Himalayan Times.
- “Execution of the Motihari-Amlekhgunj fuel pipeline project is taking longer than anticipated. The project cost today has already risen a lot and is bound to increase further if the project construction work is not started soon,” said the NOC official, adding that both Indian and Nepali authorities should coordinate to execute the project as soon as possible.
- According to the NOC official, the cost of the Motihari-Amlekhgunj oil project has increased by over Rs. 600 million over the last two-and-a-half years. This means that constructing the pipeline project today will cost more than Rs. 5 billion.
- “As IOC had stated it could start construction works on the petroleum pipeline project once at least 10 kilometres of the project’s route was fully ready, we are expecting IOC to start the pipe laying process from the Parwanipur-Pathlaiya section (stretching almost 20 km), as issues related to encroachments along this part of the planned project route have been settled,” said Sushil Bhattarai, acting deputy managing director at NOC.
The Latest
-
TechLekh Awards – Best Bikes of 2024 in Nepal Winners!The electric boom in the automotive landscape has recently changed Nepal’s four-wheeler market with new…
-
TechLekh Awards – Best Cars of 2024 in Nepal Winners!In 2024, Nepal’s automobile market saw a game-changing surge in electric vehicles (EVs). From well-known…
-
TechLekh Awards – Best Scooters of 2024 in Nepal Winners!Scooters have taken a very vital role in Nepal’s modern automotive industry. It has pretty…
-
TechLekh Awards – Best Phones of 2024 in Nepal Winners!Smartphones have become indispensable in our daily lives, fundamentally transforming how we navigate the world.…
-
Hyundai Creta Electric Coming to Nepal: Available in Two Battery OptionsHIGHLIGHTS Hyundai Creta EV price in Nepal is expected to be between Rs. 55 Lakhs…
-
GAC Aion V Debuts in Nepal: Mid-Size SUV with 650 Km NEDC RangeHIGHLIGHTS GAC Aion V price in Nepal is Rs. 64.99 Lakhs for the Elite variant…
-
Both Members of Honor X5b Series are Now Available in NepalHIGHLIGHTS Honor X5b series including base, and Plus models launched in Nepal for a starting…