The Nepal Electricity Authority (NEA) has finalized a Sigma Con as the contractor for the Balanch-Attariya Transmission Line Project, reports The Kathmandu Post.
The Details:
- Signa Con was selected through a global tender. The contractor is currently carrying a study to find out the quantity of equipment that will be needed to execute the upgradation.
- The study will take 2 months. After the study report is presented to NEA, NEA will approve the report and the equipment will be imported.
- The contractor plans to start the upgrade from May and complete it by February 2019.
- This project will upgrade the power line linking the country’s far western region to the national grid, from single circuit to double circuit. This will allow the transmission of six-phase electric power from the current power of three-phase.
- After its implementation, the power line will be able to evacuate around 180 MW of electricity in the region.
Backstory:
- The Balanch-Attariya Transmission Line was supposed to be completed in 2014 but different factors pushed back the deadline until it came into completed in November 2017.
- It is currently transmitting electricity generated by the 30 MW Chameliya Hydropower Project developed by the NEA, and the 8.5 MW Naugad Hydropower Project developed by Api Power.
The Latest
-
TVS iQube with a 2.2 kWh Battery Launched in Nepal at Rs. 2.99 Lakh!HIGHLIGHTS TVS iQube price in Nepal starts at Rs. 3 Lakhs to Rs. 4.30 Lakhs.…
-
JMEV GSE Elight EV: An Affordable Electric Sedan Coming Soon to NepalHIGHLIGHTS JMEV GSE Elight EV price in Nepal is expected to be around Rs. 54…
-
Riddara RD6 – A High-Performance Electric Pickup Truck Launched in Nepal!HIGHLIGHTS Riddara RD6 price in Nepal is Rs. 65 Lakhs It is an all-electric mid-size…