The Nepal Electricity Authority (NEA) has finalized a Sigma Con as the contractor for the Balanch-Attariya Transmission Line Project, reports The Kathmandu Post.
The Details:
- Signa Con was selected through a global tender. The contractor is currently carrying a study to find out the quantity of equipment that will be needed to execute the upgradation.
- The study will take 2 months. After the study report is presented to NEA, NEA will approve the report and the equipment will be imported.
- The contractor plans to start the upgrade from May and complete it by February 2019.
- This project will upgrade the power line linking the country’s far western region to the national grid, from single circuit to double circuit. This will allow the transmission of six-phase electric power from the current power of three-phase.
- After its implementation, the power line will be able to evacuate around 180 MW of electricity in the region.
Backstory:
- The Balanch-Attariya Transmission Line was supposed to be completed in 2014 but different factors pushed back the deadline until it came into completed in November 2017.
- It is currently transmitting electricity generated by the 30 MW Chameliya Hydropower Project developed by the NEA, and the 8.5 MW Naugad Hydropower Project developed by Api Power.
The Latest
-
Xiaomi TV S Mini LED 2026 Series Launched In Nepal: Sounds Like A Steal!HIGHLIGHTS The Xiaomi TV S Mini LED 2026 Series price in Nepal starts at Rs.…
-
Apple Mac mini M6 Launched in Nepal With 4x Faster AI PerformanceHIGHLIGHTS The Apple Mac mini M6 price in Nepal starts at Rs. 174,999 (16/256GB). The…
-
Apple Watch Ultra 4 Arrives in Nepal With Better Battery LifeHIGHLIGHTS The Apple Watch Ultra 4 price in Nepal is Rs. 1,78,500. It features the…