The Nepal Electricity Authority (NEA) has finalized a Sigma Con as the contractor for the Balanch-Attariya Transmission Line Project, reports The Kathmandu Post.
The Details:
- Signa Con was selected through a global tender. The contractor is currently carrying a study to find out the quantity of equipment that will be needed to execute the upgradation.
- The study will take 2 months. After the study report is presented to NEA, NEA will approve the report and the equipment will be imported.
- The contractor plans to start the upgrade from May and complete it by February 2019.
- This project will upgrade the power line linking the country’s far western region to the national grid, from single circuit to double circuit. This will allow the transmission of six-phase electric power from the current power of three-phase.
- After its implementation, the power line will be able to evacuate around 180 MW of electricity in the region.
Backstory:
- The Balanch-Attariya Transmission Line was supposed to be completed in 2014 but different factors pushed back the deadline until it came into completed in November 2017.
- It is currently transmitting electricity generated by the 30 MW Chameliya Hydropower Project developed by the NEA, and the 8.5 MW Naugad Hydropower Project developed by Api Power.
The Latest
-
realme C100x Finally Joins C100i in Nepal: Two Huge Batteries, One Big ProblemHIGHLIGHTS The realme C100 series price in Nepal starts at Rs. 28,999 (4/128GB). The realme…
-
Motorola Edge 70 Fusion Launching in Nepal This Week!HIGHLIGHTS The Motorola Edge 70 Fusion price in Nepal could start at Rs. 59,999 (8/128GB).…
-
Xiaomi 17T Gets Rs. 10,000 More Expensive in Nepal: Still Value for Money?HIGHLIGHTS The Xiaomi 17T price in Nepal is Rs. 99,999 for the single 12/512GB variant.…



