The government is planning to take action against Amar Construction and Sunkoshi Biruwa SL, both working on Kanti Highway, as they are likely to be unable to meet their agreement of blacktopping two road segments within mid-July.
The Details:
- The office overseeing the project is looking to impose a fine on the two contractors as their contracts cannot be extended.
- Amar Construction was to widen 9-km segment of the highway from Simat to Aale Bhanjyang while Sunkoshi Biruwa SL was working to widen the road segment from Kalche of Lalitpur to Devisthan.
- The Kanti Highway is a 90-km highway to Hetauda from Kathmandu which will significantly reduce the time.
- Currently there are two possible routes to Hetauda, one 226-km (via Mugling and Narayanghat) and another 136-km (via Palung).
- The highway track was opened in 1959. Since then it has been sixty years and the highway still has not been completed.
The Latest
-
Deepal S03: The Newest Member of Deepal’s S-Series Trying to Break Through in NepalHIGHLIGHTS Deepal S03 price in Nepal is expected to be between Rs. 40 Lakhs and…
-
Xiaomi Mobile Price in Nepal (December 2025 Updated)This is the complete list of Xiaomi mobile price in Nepal for 2025. In this…
-
Redmi A5 Sees A Price Hike Of Rs. 1,500 in Nepal!HIGHLIGHTS Redmi A5 price in Nepal is Rs. 12,499 (3/64GB) and Rs. 13,499 (4/128GB). The…