According to Nepal Electricity Authority (NEA) official, like last year, there will not be any power cuts in Kathmandu and other cities this winter as well, reports My Republica.
NEA’s spokesperson Prabal Adhikari said, “Though our efforts to increase supply have almost failed, during the upcoming dry months we will be able to supply electricity as last year, thanks to demand-side management and leakage control.”
This year, NEA came up with the plan to produce 25 MW electricity from solar plants, import additional electricity from India and save electricity through the supply of energy-efficient LED bulbs. But NEA could not follow through them. However, NEA worked well on its demand-side management. And this has put NEA in a good position for supplying electricity as last year.
Managing evening peak load, i.e. from 5:30 pm to 7:30 pm, is taken as the most challenging task for NEA. This year on 20th November, the evening peak load demand was 1248 MW which is 8 MW more than the same day last year. This shows that peak has nearly stabilized at a variance of annual average demand growth rate of 10 percent.
Adhikari said, “Behavioral changes in electricity consumption, consumers who voluntarily switched to more efficient LED bulbs, zero or very little use of inverters and inefficient equipment, and leakage control are the reasons that helped in reducing the peak-hour demand.”
Adhikari futher added that consumers had listened to their pleas not to use appliances that consume a lot of electricity during evening and morning peak hours and that they had also switched to energy-efficient LED bulbs. The use of these LEDs alone has saved around 100 MW.
This year, NEA’s solar plants plans were delayed after the Public Accounts Committee ordered a retender for the solar plants contracts. However, the directive was dismissed and the plan is now resuming again. In the same way, NEA also had to terminate the contract awarded to a Chinese contractor for building the Dhalkebar substation.
Currently, Nepal has a power deficit of 300 MW. It generates 676 MW of electricity while 272 MW is imported from India.
-
Nothing Phone (4b) Expected to Launch in Nepal: Fresh Start or (4a) Lite in Disguise?HIGHLIGHTS The Nothing Phone (4b) price in Nepal could be Rs. 45,999 for the 8/128GB…
-
realme C100i Enters Nepal with 7,000mAh Battery; C100x Launching Next MonthHIGHLIGHTS The realme C100 series price in Nepal starts from Rs. 28,999 (4/128GB). The realme…
-
Redmi Watch 6 Arrives in Nepal: Better Than the Huawei Watch Fit 5?HIGHLIGHTS The Redmi Watch 6 price in Nepal starts at Rs. 20,499. It has a…