According to a source, the World Bank is supporting the Nepal Electricity Authority’s (NEA) project to install a 25 MW solar plant. The contract of the project is to be given to a Chinese company, Raijin Energy Co.
The World Bank had agreed to provide $130 million to the government to build solar stations to reduce electric shortages, in early 2015. Amount of $37 million has already been designated to establish solar plants at Devighat and Trishuli in Nuwakot district.
Although, the construction hasn’t begun due to controversy in the selection of the contractor. The former NEA managing director, Mukesh Raj Kafle decided to hire a Chinese company to build the project.
The company was later declared unqualified by a committee of international experts. Due to which the new NEA managing director, Kulman Ghising decided to give the contract to Raijin Energy Co. But, as per PAC, the Rs 3.7 billion quoted by Raijin Energy Co was Rs. 680 million higher than earlier contract.
Public Accounts Committee (PAC) citing that it was against the procurement law directed NEA to scrap the contract. Currently, the contract is under suspension. However, the World Bank defends NEA stating that the procurement policies and practices adopted by 189 member-governments of the World Bank Group and the funding agreement signed with Nepal were followed.
-
Geely Has No Official Distributor in Nepal, Proton & Jagdamba Motors Issue StatementHIGHLIGHTS Proton and Jagadamba Motors have released a joint statement. According to the statement, Geely…
-
Hero XPulse 210 Unveiled in Nepal: Promising Big Upgrades, But No Launch Details YetHIGHLIGHTS Hero XPulse 210 is officially unveiled in Nepal at the NADA Auto Show 2025.…
-
Leapmotor B10 in Nepal: Fresh Design, Strong Value, or Missed Marks?HIGHLIGHTS Leapmotor B10 price in Nepal starts at Rs. 49.99 Lakhs and goes up to…